Through the following link you can access the history of public information procedures in the field of public sector contracting by month:
See historic
Works of the implementation project for the reconfiguration of the electrical system and instrumentation and control of phase 1 of the dismantling of the Santa María de Garoña Nuclear Power Plant
Drafting of the project and execution of the construction work of a large declassifiable warehouse and a declassification building on the site of the Santa María de Garoña Nuclear Power Plant
12-BU-4690; 54.1001/23 Autovía del Duero, A-11. Stretch: Variant of Langa de Duero-Variant of Aranda de Duero. Province of Burgos.
Execution of the works of the project of construction of remodeling of the stations between Aranda-Aranda branch. Line 102. Via
Execution of the works of reform and expansion of the assistance center MAZ M.C.S.S. #11 located in Burgos
Repair works of bm leon towed after fire
Installation works of a fall safety system in the warehouse of the Provincial Historical Archive of León.
MDEF 114 Intervention in improving energy efficiency and thermal envelope through actions on different buildings and infrastructures, Base Conde de Gazola, San Andrés del Rabanedo (León) (TC 405-06/22).
Asphalt paving works in the work CYL 7 – Environmental restoration of mining spaces in the T.M. of Velilla del río Carrión (Valdehague-Besande) Palencia, financed by the European Union through the mechanism of Recovery and Resilience - Nextgeneration EU, to be awarded by simplified open procedure
Infrastructure improvement action (AMI): project design and implementation of muretes guardabalasto and drainage adaptation between Santibáñez de la Peña and Cordovilla. Line 790.
Construction of the new Experimental Area – AREX2 (Extension of the M5 building) of the Consortium of the Center of Pulsed Lasers (CLPU). SALAMANCA – Co-financed action with PRTR-Next Generation EU funds
Building Deck Repair No. 12, Act. General Arroquia, Salamanca (TC 412-04/24)
33-SO-3420; 54,656/23. Project of humanization and urban integration of the stone bridge of Soria, including rehabilitation, located on the crossing of the road n-234, of the p.k. 349+201 at p.k. : 349+312. Province of Soria. Recovery, Transformation and Resilience Plan, Next Generation EU.
Contracting of the installation works of dry partition and false ceilings, including all the necessary material except that supplied by Tragsa, for the execution of the work: “Modernization and expansion of the BRIF base of Lubia (Soria)”, within the framework of the PRTR financed by the European Union -Nextgeneration EU, to be awarded by simplified open procedure.
Implementation of the construction project for the suppression of the crossing at the P.K. level 225/066 of the Madrid-Chamartín-Hendaya line, municipality of Matapozuelos (Valladolid)
Work to eliminate occupational risks in the Archive at the Real Chancillería de Valladolid.
Execution of the project of construction of suppression of the step at the level of the p.k. 227/324 of the Madrid-Chamartín-Hendaya line, municipality of Valdistilllas (Valladolid).
Execution of the works of the project of construction of platform of the connection of the High-speed Lines Madrid-Valladolid and Madrid-Olmedo-Zamora-Galicia in the environment of olmedo (Valladolid). Phase I.
Interior office reform and ship rehabilitation as an archive in the Canal de Castilla basin (Valladolid)