Titular: Monteria Solar, S.L.U., with C.I.F. Nº B- 88209275, and address for the purposes of notifications in calle Cardenal Marcelo Spínola, 4, 1º D, 28016 Madrid.
Description of the Facilities included in the file:
- The MONTERIA SOLAR photovoltaic plant, with an authorized installed capacity of 59.02 MW, which, according to the modified project will have a peak capacity of 65.05 MWp and an installed capacity of 55.26 MW, will be located in the municipal areas of Pozo de Guadalajara and Guadalajara (Guadalajara). The energy generated will be carried by underground lines at 30 kV to the collection substation ST Pozo I 220/30 kV, located outside the implantation, subject to processing in another file.
The rest of the evacuation infrastructures used by this plant up to the Ardoz 220 kV (REE) substation are the subject of other files.