RESOLUTIONS
Resolution of the General Directorate of Energy Policy and Mines, granting Renewable Developments FV Olmedilla, S.L. the one prior administrative authorisation and administrative authorisation for the construction of the battery storage module “BESS Hybridisation Olmedilla”, of 27.46 MW of installed power, and for its evacuation infrastructure, for its hybridization with the existing photovoltaic solar park “FV Olmedilla”, of 42 MW of installed power, located in the municipal areas of Alarcón and Valverdéjà, in the province of Cuenca.
Resolution Prior Administrative Authorization (AAP) and Administrative Construction Authorization (AAC) 09-05-2025.