Municipal terms: Brazatortas and Almodóvar del Campo (Ciudad Real)
Solar Photovoltaic Installation Espartero: Brazatortas and Almodóvar del Campo.
Substation Espartero 33/220 kV: Almodóvar del Campo.
High voltage overhead line 220kV (SE Espartero – SE Colecora): Brazatortas and Almodóvar del Campo.
Substation SE 2 Collector 220 kV: Brazatortas.
High Voltage Overhead Line 220 kV: Brazatortas.
Power: 174.00 MW nominal and 228.971 MW peak
Holder: Enel Green Power España S.L.
Projects contained:
Solar Photovoltaic Installation FV Espartero
Substation Espartero 33/220 kV
High voltage overhead line 220kV (SE Espartero – SE Colecora)
Common Infrastructure for Evacuation Knot Brazatortas 220
Substation SE 2 Colecora 220 kV
High Voltage Overhead Line 220 kV