PFot-790 AC. Photovoltaic installation Trivia of 45.04 MWp and 42.56 MWins and the hybridization generation plants Troilo of 76.61 MW of power (49.52 MWp and 46.61 MWins of photovoltaic technology and 30 MW of wind technology) and Tulpar of 50.49 MW of power (34.52 MWp and 32.49 MWins of photovoltaic technology and 18 MW of wind technology) in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Tauste (Zaragoza).
Power: 121.66 MW.
Holder: Energía Inagotable de Trivia, S.L, Energía Inagotable de Troilo, S.L y Energía Inagotable de Tulpar, S.L. Being Energía Inagotable de Trivia, S.L the promoter that represents all the companies.
Projects contained:
- Trivia photovoltaic installation of 45.04 MWp and 42.56 MWins.
- Troilo hybridization generation plant with 76.61 MW of power (49.52 MWp and 46.41 MWins of photovoltaic technology and 30 MW of wind technology).
- Tulpar hybridization generation plant of 50.49 MW of power (34.52 MWp and 32.49 MWins of photovoltaic technology and 18 MW of wind technology).
The evacuation infrastructure is included in the PEol-731 AC, PFot-677 AC and PEol-522 AC files.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 07/03/2022.
- Public Information BOE: 18/04/2022.
- Public information BOP Zaragoza: 18/04/2022.
- DIA Resolution: 17/11/2023.