- The works will end in June 2028, with a daily pipe installation rate of 200 meters, which will increase to 400 starting in the summer.
- The action advances on two simultaneous fronts: in Ramal 8A-B (Casa Bolot-Daimiel) 5.3 of the 11.8 kilometers planned have already been excavated and 3.5 kilometers of pipe of 800 mm in diameter have been installed, while today the installation of 600 mm pipe in Ramal 8A-3 (Daimiel-Cerro Cabezuelo Deposit) has begun
- The action will directly benefit more than 55,000 inhabitants of the Campo de Calatrava and Daimiel and will guarantee the supply in case of emergency to another 100,000 of the surroundings of Ciudad Real