PEol-687 AC. 30 MW AES wind installations, 36 MW Aelo, 42 MW Calasi, 36 MW Aequitas, 42 MW Arvales, 42 MW Augur, 36 MW Albuena, 36 MW Anteo, 42 MW Arete, 42 MW Axilo, 30 MW Carenna, 36 MW Insitor, 24 MW Halio and 36 MW Candelaria, and their evacuation infrastructure in the provinces of Teruel, Zaragoza and Barcelona.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Caspe (Zaragoza); Alcañiz (Teruel).
- Evacuation infrastructure: Caspe (Zaragoza); Alcañiz (Teruel); Rubí (Barcelona).
Power: 510 MW.
Holder: Inexhaustible Energy of Aes, S.L., Inexhaustible Energy of Aelo, S.L., Inexhaustible Energy of Calasi, S.L., Inexhaustible Energy of Aequitas, S.L., Inexhaustible Energy of Arvales, S.L., Inexhaustible Energy of Augur, S.L., Inexhaustible Energy of Albuena, S.L., Inexhaustible Energy of Anteo, S.L., Inexhaustible Energy of Arete, S.L., Inexhaustible Energy of Axilo, S.L., Inexhaustible Energy of Carmint, S.L., Inexhaustible Energy of Insitor, S.L., Inexhaustible Energy of Halio, S.L. and Inexhaustible Energy of Candela, S.L. Being Inexhaustible Energy of Calasi, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Wind installation Aes of 30 MW.
- Aelo wind installation of 36 MW.
- Calasi wind installation of 42 MW.
- Aequitas wind installation of 36 MW.
- Arvales wind installation of 42 MW.
- Augur wind installation of 42 MW.
- Albuena wind installation of 36 MW.
- Anteo wind installation of 36 MW.
- Wind installation Arete of 42 MW.
- Axilo wind installation of 42 MW.
- 30 MW of Carmint wind power installation.
- Wind installation Insitor of 36 MW.
- Halio wind installation of 24 MW.
- Wind installation Candelaria of 36 MW.
- Evacuation infrastructure:
SET Las Fuesas 30/132 kV.
LAAT 132 kV SET Las Fuques-SET Miraflores of 6,967 meters in length.
SET Miraflores 30/132/400 kV.
LAAT 400 kV SET Miraflores -SET Sarral CJ2DE 622 meters in length.
LAAT 220 kV SET Promotores Can Jardi-SET Can Jardi de 1.651 metros de longitud.
The rest of the shared evacuation infrastructure is included in the PEol-577 AC and PEol-556 AC files.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 07/29/2021.
- Public Information BOE: 06/04/2022.
- Public information BOP Zaragoza: 04/06/2022.
- Public information BOP Teruel: 06/04/2022.
- Public information Official Diari of the Government of Catalonia: 04/21/2022.
- DIA Resolution: 12/09/2023.
- Resolution AAP Arvales: 12/12/2023.
- Resolution AAP Augur: 12/12/2023.
- Resolution AAP Albuena: 12/12/2023.
- Resolution AAP Anteo: 12/12/2023.
- Resolution AAP Calasi: 12/12/2023.
- Resolution AAP Arete: 12/12/2023.
- Resolution AAP Aelo: 12/12/2023.
- Resolution AAP Aequitas: 12/12/2023.
- Resolution AAP Aes: 12/12/2023.
- Resolution AAP Axilo: 12/12/2023.
- Halio AAP Resolution: 12/12/2023.
- Resolution AAP Candelaria: 12/12/2023.
- Resolution AAP Insitor: 12/12/2023.
- Resolution AAP Carmint: 12/12/2023.