PEol-FV 120. Photovoltaic installation Las Majas VII C of 10.89 MW of installed power, for its hybridization with the existing wind farm “Las Majas VII C” of 49.40 MW of installed power, and its evacuation infrastructure, in the province of Zaragoza.
INFORMATION OF THE FILE:
This new project will hybridize with the existing wind farm “Las Majas VII C” of 49.40 MW of installed power, already built for autonomous processing.
Municipal terms:
- Park: Herrera de los Navarros and Villar de los Navarros (Zaragoza).
- Evacuation infrastructure: Herrera de los Navarros (Zaragoza).
Power: 10.89 MW.
Holder: South European Energy Forces XII, S.L.
Projects contained:
- Photovoltaic installation of 10.89 MWins.
- Evacuation infrastructure:
30 kV evacuation line to SET Las Majas VII.
Modification of SET Las Majas VII 30/220 kV, in the municipality of Herrera de los Navarros (Zaragoza).
The rest of the shared evacuation infrastructure is included in another file.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 02/24/2023.
- Public information BOP Zaragoza: 07/09/2023.
- DIA Resolution: 18/10/2024.
- Resolution AAP and AAC: 19/02/2025.