PFot-144, PFot-145 and PFot-146. Photovoltaic installations Centaurus IV, Centaurus V and Centaurus VI of 104.50 MWp each and its evacuation infrastructure in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Alfajarín, Perdiguera and Villamayor de Gállego (Zaragoza).
- Evacuation infrastructure: Alfajarín and Villamayor de Gállego (Zaragoza).
Power: 313.50 MWp.
Holder: Centaurus Environment, SL
Projects contained:
- Photovoltaic installation Centaurus IV of 104.50 MWp.
- Photovoltaic installation Centaurus V of 104.50 MWp.
- Photovoltaic installation Centaurus VI of 104.50 MWp.
- Evacuation infrastructure:
400 kV high voltage overhead power line from SET Alfajarín to SE Peñaflor.
The projected photovoltaic park, FV Fuendetodos 124.92 MWp, is located in the municipality of Villanueva de Hueva, although for the underground evacuation line in medium voltage (30 kV) it will also affect the municipality of Fuendetodos. Its evacuation infrastructures, Subestacion Fuendetodos Colecora 30 / 400 kV and the evacuation line from said substation to the connection point in the substation Fuendetodos 400 kV, are the subject of other files.
STATUS OF THE FILE:
Prior Administrative Authorization, Environmental Impact Statement, Construction Administrative Authorization and Public Utility Statement:
- Starting date for processing: 19/09/2020.
- Public Information BOE: 11/10/2020.
- Public information BOP Zaragoza: 11/23/2020.
- DIA Resolution: 18/05/2022.
- Resolution AAP Centaurus IV: 20/04/2023.
- Resolution AAP Centaurus V: 20/04/2023.
- Resolution AAP Centaurus VI: 20/04/2023.
- DIA Modification Resolution: 21/05/2024.
Request for the modification of the prior administrative authorization and the administrative authorization of construction.
- Public information BOE Centaurus IV: 29/05/2023.
- Public information BOE Centaurus V: 29/05/2023.
- Public information BOE Centaurus VI: 30/05/2023.
- Public information BOP Zaragoza Centaurus IV: 30/05/2023.
- Public information BOP Zaragoza Centaurus V: 30/05/2023.
- Public information BOP Zaragoza Centaurus VI: 30/05/2023.
- Resolution modification AAP and AAC Centaurus IV: 16/07/2024.
- Resolution modification AAP and AAC Centaurus V: 15/07/2024.
- Resolution modification AAP and AAC Centaurus VI: 16/07/2024.