PEol-851. Florín wind installation of 105.4 MWins and its evacuation infrastructure in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Borja, Ambel, Bulbuente and Ainzón (Zaragoza).
- Evacuation infrastructure: Borja, Ainzón, Bureta, Alberite de San Juan, Magallón, Agón and Bisimbre (Zaragoza).
Power: 105.4 MW.
Holder: Green Capital Development 67, SLU.
Projects contained:
- Florín wind installation of 105.4 MW.
- Evacuation infrastructure:
Florín 30/220 kV transformer substation, in the municipality of Borja, in Zaragoza.
High voltage airline LAAT 220 kV SET Florín-SET Promoters Magallón, of 19.22 kilometers, in the municipal areas of Borja, Ainzón, Bureta, Alberite de San Juan, Magallón, Agón and Bisimbre, in Zaragoza.
Transformative substation Promoters Magallón 220/400 kV, in the municipality of Magallón, in Zaragoza.
High voltage airline LAAT 400 kV SET Promoters Magallón-SET Magallón, 0.54 kilometers, in the municipality of Magallón, in Zaragoza.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 14/08/2023.
- Public Information BOE: 11/12/2023.
- Public information BOP Zaragoza: 15/12/2023.
- DIA Resolution: 24/11/2025.