PEol-750 AC. 49.5 MW Suki, 42.2 MW Suzaku, 49.5 MW Son, 49.5 MW Sirio, 49.5 MW Saya, 49.5 MW Ryu, 49.5 MW Sabik and 49.5 MW Sakura wind farms, and their evacuation infrastructures, in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Ainzón, Alberite de San Juan, Ambel, Borja, Bureta, Fuendejalón, Tabuenca, Tallovers, Trasobares and Tierga (Zaragoza).
- Evacuation infrastructure: Ainzón, Agón, Alberite de San Juan, Bisimbre, Bureta, Fréscano, Magallón, Tabuenca, Tallovers and Trasobares (Zaragoza).
Power: 388.7 MW.
Holder: Inexhaustible Energy of Suki, S.L., Inexhaustible Energy of Suzaku, S.L., Inexhaustible Energy of Son, S.L., Inexhaustible Energy of Sirio, S.L., Inexhaustible Energy of Saya, S.L., Inexhaustible Energy of Ryu, S.L., Inexhaustible Energy of Sabik, S.L. and Inexhaustible Energy of Sakura, S.L. Being Inexhaustible Energy of Sakura, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Suki wind installation of 49.5 MW.
- Suzaku wind installation of 42.2 MW.
- Wind installation They are of 49.5 MW.
- Syrian wind installation of 49.5 MW.
- Saya wind installation of 49.5 MW.
- Ryu wind installation of 49.5 MW.
- Sabik wind installation of 49.5 MW.
- Sakura wind installation of 49.5 MW.
- Evacuation infrastructure:
Electrical substation SET Tabuenca 2.
High voltage overhead line LAAT 220 kV SET Tabuenca 2 30/220 kV-SET Frescano 220/440 kV, 31,308 kilometers in length.
Electrical substation SET Tabuenca 1.
The rest of the evacuation infrastructure is included in the PFot-753 AC file.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 01/03/2022.
- Public Information BOE: 18/04/2022.
- Public information BOP Zaragoza: 18/04/2022.
- DIA Resolution: 17/11/2023.
- Resolution AAP Suki: 9/10/2024.
- Resolution AAP Sazaku: 09/10/2024.
- Resolution AAP Are: 09/10/2024.
- Syrian AAP Resolution: 09/10/2024.
- Resolution AAP Saya: 09/10/2024.
- Resolution AAP Ryu: 09/10/2024.
- Resolution AAP Sabik: 09/10/2024.
- Resolution AAP Sakura: 09/10/2024.