PEol-740 AC. 42 MW Napeas, 42 MW Lazlos, 48 MW Dexitea, 30 MW Kelpie, 42 MW Incitatus, 48 MW Bayard, 48 MW Buraq and 30 MW Grani wind installations in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Ejea de los Caballeros and Tauste (Zaragoza).
Power: 330 MW.
Holder: Inexhaustible Energy of Napeas S.L., Inexhaustible Energy of Lazlos S.L., Inexhaustible Energy of Dexitea S.L., Inexhaustible Energy of Kelpie S.L., Inexhaustible Energy of Incitatus S.L., Inexhaustible Energy of Bayard S.L., Inexhaustible Energy of Buraq S.L. and Inexhaustible Energy of Grani S.L. Being Inexhaustible Energy of Incitatus S.L. The promoter that represents all the mercantiles.
Projects contained:
- Napeas wind installation of 42 MW.
- Lazlos wind installation of 42 MW.
- Dexitea wind installation of 48 MW.
- Kelpie wind installation of 30 MW.
- Incitatus wind installation of 42 MW.
- Bayard wind installation of 48 MW.
- Buraq wind installation of 48 MW.
- Grani wind installation of 30 MW.
- The evacuation infrastructure is included in the PEol-731 AC, PEol-522 AC and PFot-677 files.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 02/21/2022.
- Public Information BOE: 18/04/2022.
- Public information BOP Zaragoza: 18/04/2022.
- DIA Resolution: 13/11/2023.