PEol-722 AC. 49.5 MW Keneo, 49.5 MW Kaori, 49.5 MW Kari, 49.5 MW Kasumi, 27.5 MW Keiko and 27.33 MW Kirin wind farms, and their evacuation infrastructure in the provinces of Zaragoza, Navarra and La Rioja.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Asín, Biel, Luesia, Orés and Uncastillo (Zaragoza).
- Evacuation infrastructure: Orés, Luesia, Biota, Uncastillo, Sáabas and Castiliscar (Zaragoza); Carcastillo, Cáseda, Gallipienzo, Murillo el Frutos, Ujué, Pitillas, Beire, Olite, Marcilla, Peralta, Caparroso, Villafranca, Cadreita, Valtierra and Castejón (Navarra); and Alfaro (La Rioja).
Power: 252.83 MW.
Holder: Inexhaustible Energy of Keneo, S.L., Inexhaustible Energy of Kaori, S.L., Inexhaustible Energy of Kari, S.L., Inexhaustible Energy of Kasumi, S.L., Inexhaustible Energy of Keiko, S.L. and Inexhaustible Energy of Kirin, S.L. Being Inexhaustible Energy of Keneo, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Keneo wind installation of 49.5 MW.
- Kaori wind installation of 49.5 MW.
- Kari wind installation of 49.5 MW.
- Kasumi wind installation of 49.5 MW.
- Keiko wind installation of 27.5 MW.
- Kirin wind installation of 27.33 MW.
- Evacuation infrastructure:
Electrical substation SET Asín.
Electrical substation SET Alera.
High voltage airline LAAT 400 kV Nudo Malpica – Nudo Olite.
Línea aérea de alta tensión LAAT 400 kV SET Asin – SET Promotores Castejon.
LAAT 400 kV SET Asín – Nudo Malpica, 12.513 km long, high-voltage airline segment.
Stretch of high-voltage airline LAAT 400 kV Nudo Olite – SET Castejón Promoters, of 38,148 kilometers.
The rest of the shared evacuation infrastructure is included in the files Expte SAT – 11133 and Expte 5041, in the Foral Community of Navarra.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 09/28/2021.
- First public information BOE: 12/23/2021.
- First public information BOP Zaragoza: 12/24/2021.
- First public information BOP Navarra: 03/01/2022.
- First public information BOP La Rioja: 12/28/2021.
- Second public information BOE: 23/05/2022.
- Second public information BOP Zaragoza: 24/05/2022.
- Second public information BOP Navarra: 27/05/2022.
- DIA Resolution: 04/10/2023.
- Resolution AAP Keneo: 23/10/2024.
- Resolution AAP Kaori: 04/01/2024.
- Resolution AAP Kari: 04/01/2024.
- Resolution AAP Kasumi: 04/01/2024.
- Resolution AAP Keiko: 04/01/2024.
- Resolution AAP Kirin: 10/10/2024.