PEol-614 AC. Muka, Mira, Mizar, Nara, Narumi and Rai wind installations of 49.5 MW each.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Biota and Ejea de los caballeros (Zaragoza).
Power: 297 MW.
Holder: Inexhaustible Energy of Muka S.L., Inexhaustible Energy of Mira S.L., Inexhaustible Energy of Mizar S.L., Inexhaustible Energy of Nara S.L., Inexhaustible Energy of Narumi S.L. and Inexhaustible Energy of Rai S.L. Being Inexhaustible Energy of Narumi S.L. The promoter that represents all the mercantiles.
Projects contained:
- Muka wind installation of 49.5 MW.
- Mira wind installation of 49.5 MW.
- Mizar wind installation of 49.5 MW.
- Nara wind installation of 49.5 MW.
- Narumi wind installation of 49.5 MW.
- Rai wind installation of 49.5 MW.
The evacuation infrastructure is included in the PEol-522 AC and PFot-677 files.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 27/07/2021.
- Public Information BOE: 11/17/2021.
- Public information BOP Zaragoza: 11/18/2021.
- DIA Resolution: 10/23/2023.
- Resolution AAP Narumi: 22/01/2024.
- Resolution AAP Rai:22/01/2024.
- Resolution AAP Mizar:22/01/2024.
- Resolution AAP Muka:22/01/2024.
- Resolution AAP Nara:22/01/2024.