PEol-271 AC. Diana wind installations of 88.2 MW and Vientos del Sur of 63 MW and its evacuation infrastructure in the provinces of Zaragoza and Navarra.
INFORMATION OF THE FILE:
Municipal terms:
- Parks: Ainzón, Bureta and Fuendejalón, in the province of Zaragoza.
- Evacuation infrastructure: Malón, Tarazona, Vera de Moncayo, Bulbuente, Ambel, Borja, Ainzón and Bureta (Zaragoza); Tudela, Cascante, Tulebras and Barillas (Navarra).
Power: 151.2 MW.
Holder: Green Capital Power, SL
Projects contained:
- Diana wind installation of 88.2 MW.
- Wind installation Vientos del Sur of 63 MW.
- Evacuation infrastructure:
SET Diana 30/220 KV: Transformer substation with transformer power 220/30 kV of 450 MVA.
LAAT 220 kV (private): first stretch from SET Diana to SET Tudela Promoters: duplex airline 220 kV of 34.25 kilometers in length and conductor 402-AL1/52-ST1A (LA-455).
SET Tudela Promoters 220 KV (shared): electric substation without transformation with 3 positions of conventional outdoor air line (AIS) to evacuate the energy of the wind farms Diana, Vientos del Sur and the photovoltaic plants PSFV Tudela I, PSFV Tudela II and Serna II Solar PV.
LAAT 220 kV (shared): second stretch from SET Tudela Promoters to SET Tudela 220: duplex airline of 220 kV of 7.04 kilometers in length and conductor 402-AL1/52-ST1A (LA-455).
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 22/12/2020.
- Public Information BOE: 04/14/2021.
- Public information BOP de Zaragoza: 04/09/2021.
- Public information BOP of Navarra: 03/30/2021.
- DIA Resolution: 12/22/2022.
- Dismissive resolution of the AAP of Diana: 15/04/2024.
- Dismissive resolution of the AAP of Vientos del Sur: 15/04/2024.