PEol-250 AC. San Cristóbal, Pedrecha and Cabezuela wind installations of 49.5 MW each and their evacuation infrastructures in the provinces of Soria and Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Cañamaque, Nolay, Velilla de los Ajos, Maján, Serón de Nágima, Torlengua and Cihuela (Soria).
- Evacuation infrastructure: Velilla de los Ajos, Serón de Nágima, Torlengua and Cihuela (Soria); Boldalba, Embid de Ariza, Cetina, Contamina, Alhama de Aragón, Bubierca, Ateca and Terrer (Zaragoza).
Power: 148.5 MW.
Holder: Green Capital Power, SL
Projects contained:
- Wind installations San Cristóbal, Pedrecha and Cabezuela of 49.5 MW each.
- Evacuation infrastructure:
Underground lines of 30 kV.
Collection substation Pedrecha 30/400 KV.
High Voltage Overhead Line 400 kV from SET Pedrecha to SET Colecora Terrer.
Substation promoters Terrer 30/400 KV (Green Capital Power, S.L., Enel Green Power, SL and Jorge Energy, S.L).
Línea aérea de alta tensión 400 KV SET Colectora Terrer- SET Terrer (REE),( Green Capital Power, S.L., Enel Green Power, SL and Jorge Energy, S.L).
STATUS OF THE FILE
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 18/12/2020.
- Public Information BOE: 7/05/2021.
- Public information BOP Zaragoza: 06/10/2021.
- Public information BOP Soria: 05/21/2021.
- DIA Resolution: 13/01/2023.
- Resolution AAP Cabezuelas: 04/24/2023.
- Resolution AAP San Cristobal: 25/04/2023.
- Resolution AAP Pedrecha: 25/04/2023.
Request for the modification of the prior administrative authorization and the administrative authorization of construction.
- Public information BOE Cabezuelas: 06/06/2023.
- Public information BOP Zaragoza Cabezuelas: 09/06/2023.
- Public information BOP Soria Cabezuelas: 12/06/2024.
- Public information BOE Pedrecha: 06/13/2023.
- Public information BOP Soria Pedrecha: 14/06/2023.
- Public information BOE San Cristóbal: 13/06/2023.
- Public information BOP Soria San Cristobal:14/06/2023.
- Resolution AAP and AAC BOE San Cristobal: 14/05/2024.
- Resolution AAP and AAC BOE Cabezuelas: 14/05/2024.
- Resolution AAP and AAC BOE Pedrecha: 14/05/2024.
Request for declaration, in particular, of public utility:
- Public information BOE Cabezuelas: 30/10/2024.
- Public information BOP Soria Cabezuelas: 16/10/2024.
- Public information BOP Zaragoza Cabezuelas: 08/11/2024.
- Public information BOE Pedrecha: 30/10/2024.
- Public information BOP Soria Pedrecha: 21/10/2024.
- Public information BOE San Cristóbal: 06/11/2024.
- Public information BOP Soria San Cristóbal: 6/11/2024.
- Resolution DUP BOE Cabezuelas: 19/06/2025.
- Resolution DUP BOE Pedrecha: 19/06/2025.
- Resolution DUP BOE San Cristobal: 19/06/2025.