PEol-196. 180 MW of Tico wind power plant and its evacuation infrastructure in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Villar de los Navarros (Zaragoza).
- Evacuation infrastructure: Villar de los Navarros, Azuara and Moyuela (Zaragoza).
Power: 180 MW.
Holder: Tico Wind Farm, S.L.
Projects contained:
- 180 MW of Tico wind power plant.
- Evacuation infrastructure:
Underground lines of 33 kV.
Substation Transformadora Villar de los Navarros 33/220 kV.
220 kV High Voltage Overhead Line from SET Villar de los Navarros to SET Muniesa Promoters, via the 220 kV Las Majas VIID-Muniesa Promoters Power Line.
STATUS OF THE FILE:
Prior administrative authorization, environmental impact statement and administrative construction authorization:
- Starting date for processing: 08/05/2018.
- First public information BOE: 02/06/2018.
- First public IP BOP Zaragoza: 06/19/2018.
- DIA Resolution: 12/17/19.
- AAP Resolution: 01/16/2020.
- Second public information BOE: 08/08/2020.
- Resolution AAP and AAC: 02/23/2021.
- Amended resolution AAP and AAC: 04/05/2021.
Declaration of Public Utility:
- Start order date: 02/10/2020.
- Public Information BOE: 29/10/2020.
- DUP Resolution: 04/13/2021.
Expropriations: