PFot-285. Mudéjar photovoltaic installation of 235 MWp and its evacuation infrastructure in the province of Teruel.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Alcañiz, Hijar and Andorra (Teruel).
- Evacuation infrastructure: Alcañiz, Hijar and Andorra (Teruel).
Power: 235 MWp.
Holder: Enel Green Power España, S.L.U.
Projects contained:
- Photovoltaic installation Mudéjar of 235 MWp.
- Evacuation infrastructure:
Airline 220 kV (A2).
Underground line 220 kV (A2).
SET “ST 09” 220/33 kV.
SET “ST 10” 220/33 kV.
SET “ST 02” 220/33 kV.
The rest of the evacuation infrastructure is not part of this dossier.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 07/03/2020.
- Public Information BOE: 03/08/2021.
- Public information BOP Teruel: 04/03/2021.
- DIA Resolution: 14/01/2022.
- AAP Resolution: 08/17/2022.
Administrative authorization of construction and declaration, in particular, of public utility:
- Public Information BOE: 30/03/2023.
- Public information BOP Teruel: 03/28/2023.
- Resolution AAC and DUP: 5/12/2023.
Expropriations: