PEol-FV-180. Photovoltaic installation Tardienta I, of 49.4 MW of installed power, for its hybridization with the existing wind farm Tardienta I, of 49.5 MW of installed power, and its evacuation infrastructure, in the province of Huesca.
INFORMATION OF THE FILE:
This project will hybridize with the existing wind farm “Tardienta I” of 49.5 MW installed capacity, already built for autonomous processing.
Municipal terms:
Park: Almudévar (Huesca).
Evacuation infrastructure: Almudévar and Tardienta (Huesca).
Power: 49.4 MWins
Holder: EDP Renewables Spain, S.L.U.
Projects contained:
Photovoltaic installation of 49.4 MWins.
Evacuation infrastructure:
Extension of the existing electric substation Tardienta 20/220 kV.
The rest of the shared evacuation infrastructure is included in another file.
STATUS OF THE FILE:
Environmental impact statement and prior administrative authorization: