PEol 637 AC. Tau, Sigma, Teorema, Perseus, Escudo, Pavo, Fornax, Superelipse, Orion and Sarin wind installations of 49.5 MW each, Pictor of 16 MW and Hadar of 25.25 MW and their evacuation infrastructure in the provinces of Huesca, Zaragoza and Lleida.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Almudévar, Gurrea de Gállego, Torralba de Aragón, Tardienta, Sangarrén, Barbués, Torres de Barbués and Vicién (Huesca); Zuera and Leciñena (Zaragoza).
- Evacuation infrastructure: Gurrea de Gállego, Almudévar, Laluenga y Tardienta (Huesca); Isona I Conca Dellà (Lleida).
Power: 536.25 MW.
Holder: Inexhaustible Energy of Tau, S.L., Inexhaustible Energy from Sigma, S.L., Energía Inagotable de Teorema, S.L., Energía Inagotable de Perseus, S.L., Inexhaustible Energy of Escudo, S.L., Inexhaustible Energy of Pavo, S.L., Inexhaustible Energy from Fornax. SL, Inexhaustible Energy of Superelipse, S.L., Inexhaustible Energy of Orion, S.L., Inexhaustible Energy of Sarin, S.L., Inexhaustible Energy of Pictor, S.L. and Inexhaustible Energy of Hadar, S.L. It is considered Energía Inagotable de Escudo, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Tau wind installation of 49.50 MW.
- Sigma wind installation of 49.50 MW.
- Teorema wind installation of 49.50 MW.
- Perseus wind installation of 49.50 MW.
- Wind installation Shield of 49.50 MW.
- Pavo wind installation of 49.50 MW.
- Fornax wind installation of 49.50 MW.
- Superellipse wind installation of 49.50 MW.
- Orion wind installation of 49.50 MW.
- Sarin wind installation of 49.50 MW.
- Pictor wind installation of 16 MW.
- Hadar wind installation of 25.25 MW.
- Evacuation infrastructure:
SET Saint George 30/220 kV.
LAAT 220kV SET San Jorge 30/220 kV - SET Almudévar 30/220/400 kV de 12,301 kilómetros de longitud.
SET Almudévar 30/220/400 kV.
LAAT 400kV SET Almudévar 30/220/400 kV - SET Laluenga I4 30/400 kV, tramo de 1,86 kilómetros de longitud.
SET Laluenga I4 30/400 kV.
LAAT 400kV SET Laluenga I4 30/400 kV - SET Isona 400 kV REE, de 1,756 kilómetros de longitud.
SET Tardienta 30/220 kV.
LAAT 220 kV SET Tardienta 30/220 kV – SET Almudévar 30/220/400 kV, de 6,6 kilómetros de longitud.
The rest of the shared evacuation infrastructure is included in the PEol 525 AC file.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 07/22/2021.
- Public information BOE 07/02/2022.
- Public information BOP Huesca: 04/02/2022.
- Public information BOP Zaragoza: 17/03/2022.
- Public information BOP Lleida: 07/02/2022.
- DIA Resolution: 28/08/2023.
- Resolution AAP Tau: 24/11/2023.
- AAP Sigma resolution: 24/11/2023.
- Resolution AAP Theorem: 24/11/2023.
- Resolution AAP Perseus: 24/11/2023.
- Resolution AAP Shield: 24/11/2023.
- Resolution AAP Turkey: 24/11/2023.
- Resolution AAP Orion: 24/11/2023.
- Resolution AAP Sarin: 24/11/2023.
- Resolution AAP Pictor: 24/11/2023.
- Resolution AAP Fornax: 25/11/2024.
Administrative Building Authorization Resolutions:
- Resolution AAC Tau: 29/05/2025.
- AAC Sigma resolution: 29/05/2025.
- Resolution AAC Theorem: 29/05/2025.
- Resolution AAC Perseus: 29/05/2025.
- Resolution AAC Shield: 29/05/2025.
- Resolution AAC Turkey: 29/05/2025.
- Resolution AAC Orion: 29/05/2025.
- Resolution AAC Sarin: 29/05/2025.
- Resolution AAC Pictor: 29/05/2025.