PEol-563 AC. Nembus, Osa Menor, Sextans and Lyra wind installations of 49.5 MW each and their evacuation infrastructure in the provinces of Huesca, Zaragoza, Tarragona and Barcelona.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Lanaja, Lalueza, Poleñino and Sariñena (Huesca).
- Evacuation infrastructure: Lanaja and Peñalba (Huesca); Bujaraloz and Caspe (Zaragoza); Banyeres del Penedés and L’Alborç (Tarragona) and Castellet i La Gornal (Barcelona).
Power: 198 MW.
Holder: Inexhaustible Energy of Nembus, S.L., Inexhaustible Energy of Osa Menor, S.L., Inexhaustible Energy of Sextans, S.L. and Inexhaustible Energy of Lyra, S.L. Being Inexhaustible Energy of Osa Menor, S.L. The promoter that represents the group of mercantiles.
Projects contained:
- Nembus wind installation of 49.5 MW.
- Osa Menor wind installation of 49.5 MW.
- Sextans wind installation of 49.5 MW.
- Lyra wind installation of 49.5 MW.
- Evacuation infrastructure:
Electrical substation transformer SET Castellet West 30/400 kV.
High voltage line LAAT 400 kV LAAT SET Castellet West – CS Castellet of 0,307 kilometers in length.
High voltage line LAAT 400 kV CS Castellet - SET Promoters Castellet of 36,640 kilometers in length.
Transformer electrical substation SET Promoters Castellet 400/220 kV.
High voltage line LAAT 220 kV SET Promoters Castellet - SET Castellet REE 220 kV of 0.316 kilometers in length.
The rest of the evacuation infrastructure is included in the PEol-556, PFot-539 AC and PEol-540 files.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 06/17/2021.
- Public Information BOE: 26/10/2021.
- Public information BOP Zaragoza: 10/28/2021.
- Public information BOP Huesca: 25/10/2021.
- Public information Official Diari of the Government of Catalonia: 11/17/2021.
- DIA Resolution: 18/07/2023.
- Resolution AAP Nembus: 18/10/2023.
- Resolution AAP Osa Menor: 18/10/2023.
- Resolution AAP Sextans: 18/10/2023.
- Resolution AAP Lyra: 18/10/2023.