PEol-525 AC. Omega, Kappa, Órbita, Ómicron, Lambda and Iota wind installations of 49.5 MW each and their evacuation infrastructure in the provinces of Huesca and Lleida.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Alcalá de Gurrea, Gurrea de Gállego and Almudévar (Huesca).
- Evacuation infrastructure: Almudévar, Tardienta, Sangarrén, Monflorite-Lascasas, Albero Alto, Argavieso, Alcalá del Obispo, Blecua y Torres, Antillón, Angüés, Pertusa, Barbuñales, Laluenga, Berbegal, Ilche, Castejón del Puente, Monzón, Almunia de San Juan, Azanuy-Alins, Peralta de Calasanz, Benabarre, Tolva, Viacamp and Litera and Montaavana (Terrassa, Terrassa)
Power: 297 MW.
Holder: Inexhaustible Energy of Omega, S.L., Inexhaustible Energy of Kappa, S.L., Inexhaustible Energy of Órbita, S.L., Inexhaustible Energy of Ómicron, S.L., Inexhaustible Energy of Lambda, S.L. and Inexhaustible Energy of Iota, S.L. The company Energía Inagotable de Kappa, S.L. It is the promoter that represents all of the mercantiles.
Projects contained:
- Omega wind installation of 49.5 MW.
- Kappa wind installation of 49.5 MW.
- Orbit wind installation of 49.5 MW.
- Omicron wind installation of 49.5 MW.
- Lambda wind installation of 49.5 MW.
- Iota wind installation of 49.5 MW.
- Evacuation infrastructure:
SET Valsalada 30/400 kV.
LAAT 400 kV from the SET Valsalada to the SET Laluenga I2.
SET Laluenga I2 30/400 kV.
LAAT 400 kV from the SET Laluenga I2 to the SET Promoters Isona.
SET Promoters Isona 400 kV / 220 kV.
LAAT 220 kV from SET Promoters Isona to the SET Isona node owned by REE.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 06/05/2021.
- Public Information BOE: 09/09/2021.
- Public information BOP Huesca: 24/09/2021.
- Public information BOP Lleida: 09/10/2021.
- DIA Resolution: 06/06/2023.
- Resolution AAP Omega: 04/09/2023.
- Resolution AAP Kappa: 30/08/2023.
- Resolution AAP Iota: 04/09/2023.
- Resolution AAP Lambda: 04/09/2023.
- Resolution AAP Ómicron: 04/09/2023.
- Resolution AAP Orbit: 04/09/2023.
Modification of prior administrative authorisation and administrative construction authorisation:
- Public Information BOE: 12/09/2024.
- Public information BOP Huesca: 13/09/2024.
- Public information BOP Lleida: 09/09/2024.
- Resolution modification of AAP and AAC Omega: 03/07/2025.
- Resolution modification of AAP and AAC Kappa: 02/07/2025.
- Resolution modification of AAP and AAC Iota: 03/07/2025.
- Resolution modification of AAP and AAC Lambda: 03/07/2025.
- Resolution modification of AAP and AAC Ómicron: 03/07/2025.
- Resolution modification of AAP and AAC Orbit: 03/07/2025.