PFot-321 Terrer Solar photovoltaic installation of 124.72 MWins and its evacuation infrastructure in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Moros, Ateca and Terrer (Zaragoza).
- Evacuation infrastructure: Moros, Ateca and Terrer (Zaragoza).
Power: 124.72 MWins.
Holder: JORGE ENERGY I, S.L.
Projects contained:
- Solar Terrer photovoltaic installation of 124.72 MWins.
- Evacuation infrastructure:
Elevating substation Terrer 132/30 kV (shared with projects being processed by the Provincial Service of Industry, Competitiveness and Business Development of Zaragoza with n/file AT 2020/150).
High voltage overhead line in 132kV, with origin in substation Terrer 132/ 30 kV and end in substation Colecora Terrer 400/132 kV, of simple circuit, arrangement in staggered, of 3,307 km in length (shared with projects in process by the Provincial Service of Industry, Competitiveness and Business Development of Zaragoza with n/file AT 2020/151).
Terrer 400/132 kV Collection Substation (shared with projects in progress by the Provincial Service of Industry, Competitiveness and Business Development of Zaragoza with n/file AT 2020/218).
High voltage overhead line 400 kV from Terrer 400/132 kV substation to REE’s Terrer 400 kV substation, simple circuit, layer and flag arrangement and 6,404 Km in length. (shared with projects in progress by the Provincial Service of Industry, Competitiveness and Business Development of Zaragoza with n/file AT 2020/217).
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 04/12/2022.
- Public Information BOE: 01/25/2021.
- Public information BOP Zaragoza: 26/01/2021.
- DIA Resolution: 20/06/2022.
- AAP Resolution: 06/11/2022
Administrative authorization of construction and declaration of public utility:
- Starting date for processing: 06/10/2021.
- Public information BOE 06/04/2022
- Public information BOP Zaragoza: 04/04/2022.
- Resolution AAC and DUP: 01/17/2023.
Expropriations:
- Resolution calling for the lifting of previous BOE minutes: 06/06/2023.
- Resolution calling for the lifting of previous acts of the BOP Zaragoza: 08/06/2023.
- Resolution calling for the collection of BOE payment records: 16/09/2024.
- Resolution calling for the collection of payment minutes BOP Zaragoza: 01/10/2024.