PEol-634 AC. Leo and Officus wind installations of 49.5 MW each and their evacuation infrastructure in the provinces of Zaragoza and Huesca.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Zuera, Leciñena and San Mateo de Gállego (Zaragoza); Tardienta, Robres and Torralba de Aragón (Huesca).
- Evacuation infrastructure: Zuera, Leciñena and San Mateo de Gállego (Zaragoza); Tardienta, Robres and Torralba de Aragón (Huesca).
Power: 99 MW.
Holder: Inexhaustible Energy of Leo, S.L. and Inexhaustible Energy of Officus, S.L. Being Inexhaustible Energy of Leo, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Leo wind installation of 49.5 MW.
- Wind installation Officus of 49.5 MW.
The evacuation infrastructure is included in the PEol-556 file.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 16/08/2021.
- Public Information BOE: 02/14/2022.
- Public information BOP Zaragoza: 15/02/2022.
- Public information BOP Huesca: 14/02/2022.
- DIA Resolution: 28/08/2023.
- Resolution AAP Leo: 05/11/2024.
- Resolution AAP Officus: 05/11/2024.