EXTENSION OF THE MAGALLÓN SUBSTATION IN THE PARK OF 400/220 KV TO INSTALL A NEW 400/220KV TRANSFORMATION BENCH IN THE PROVINCE OF ZARAGOZA.
- PROJECT: Request for prior administrative authorization and administrative authorization of construction of RED ELÉCTRICA, which has planned expansion of the Magallón Substation in the park of 400/220 kV, to install a new transformation bank 400/220 kV in three-phase configuration of 600 MVA constituted by 3 single-phase units of 200 MVA, and connection to the park of 220 kV with insulated cable, in the municipality of Magallón in the province of Zaragoza.
- PROMOTER: Red Eléctrica de España, S.A.U.
- OBJECTIVE: Processing of the request for prior administrative authorization and administrative authorization of construction of RED ELÉCTRICA, which has planned the expansion of the Magallón Substation in the park of 400/220 kV, to install a new 400/220 kV transformation bank in the province of Zaragoza.