PFot-444. Fuendetodos photovoltaic installation of 124.92 MWp and its evacuation infrastructure in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Villanueva de Huerva (Zaragoza).
- Evacuation infrastructure: Fuendetodos and Villanueva de Huerva (Zaragoza).
Power: 124.92 MWp.
Holder: Iberdrola Renewables Aragón, S.A.U.
Projects contained:
- Fuendetodos photovoltaic installation of 124.92 MWp.
- Evacuation infrastructure.
Underground evacuation line in medium voltage (30 kV).
The rest of the evacuation infrastructure is not part of this dossier.
STATUS OF THE FILE:
Prior Administrative Authorization, Environmental Impact Statement, Construction Administrative Authorization and Public Utility Statement:
- Starting date for processing: 12/23/2020.
- Public Information BOE: 05/24/2021.
- Public information BOP Zaragoza: 05/25/2021.
- DIA Resolution: 02/01/2023.
- AAP Resolution: 05/04/2023.
Modification of the prior administrative authorization and the administrative authorization of construction.