PFot-322 AC. Solar Wheel photovoltaic installation of 292 MWp and its evacuation infrastructure in the province of Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Pedrola, Plasencia de Jalón and Rueda de Jalón (Zaragoza).
- Evacuation infrastructure: Pedrola, Plasencia de Jalón and Rueda de Jalón (Zaragoza).
Power: 292 MWp.
Holder: Synergy Aragonesa, S.L.
Projects contained:
- Solar Wheel photovoltaic installation of 292 MWp.
- Evacuation infrastructure:
Photovoltaic substation Rueda 220/30 kV.
High voltage overhead line in 220 kV, with origin in Photovoltaic substation Rueda and final in Pre-Rueda 400/220 kV, divided two sections:
The first section, of simple circuit and exclusive use for the photovoltaic solar plant, staggered arrangement, of 1,833 km in length and with origin in the Rueda Photovoltaic Substation and final in support number 8 of the LAAT 220 kV Fotovoltaic Wheel-Pre-Wheel.
The second section, double circuit, hexagon arrangement, of 6,680 km in length and with origin in support number 8 of the LAAT 220kV Photovoltaic Wheel-Pre-Wheel and final in the Pre-Wheel substation. The supports of this section are shared with the LAAT 220kV Wind Wheel – Pre-Wheel for evacuation of the JALON 2050 wind farm (file SGEE/PEol-432 of the General Subdirectorate of Electrical Energy), occupying the wind farm circuit on the west side and the photovoltaic installation circuit on the east side of the line.
Pre-Wheel Substation 400/220 kV. Shared with the Jalón 2050 wind farm (SGEE/PEol-432 file of the General Subdirectorate of Electrical Energy).
High voltage overhead line 400 kV from Pre-Rueda substation to Rueda de Jalón substation 400 kV from REE (link installation). Shared with the Jalón 2050 wind farm (SGEE/PEol-432 file of the General Subdirectorate of Electrical Energy).
STATUS OF THE FILE:
Prior administrative authorization, environmental impact statement and declaration of public utility:
- Starting date for processing: 09/12/2020.
- Public Information BOE: 20/01/2021.
- Public information BOP Zaragoza: 20/01/2021.
- Second public information BOE: 02/24/2021.
- Second Public Information BOP Zaragoza: 01/03/2021.
- DIA Resolution: 01/17/2023.
- BOE Error Correction: 31/05/2023.
Administrative authorization of construction:
- Starting date for processing: 11/29/2021.
- Public Information BOE: 04/13/2022.
- Public information BOP Zaragoza: 13/04/2022.
- Resolution AAP, AAC and DUP: 26/01/2024.