PEol-475. Muno wind installation of 273,275 MW and its evacuation infrastructure in the provinces of Zaragoza and Navarra.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Uncastillo, Sáabas, Castiliscar and Sos del Rey Catlico (Zaragoza).
- Evacuation infrastructure: Castiliscar, Sos del Rey Catlico (Zaragoza); Carcastillo, Cáseda, Gallipienzo, Murillo el Frutos, Ujué, Beire, San Martín de Unx, Olite, Tafalla, Pueyo, Garínoain, Barásoain, Olóriz, Unzué and Tiebas-Muruarte (Navarre).
Power: 273,275 MW.
Holder: Green Capital Development 74 SLU.
Projects contained:
- Muno wind installation of 273,275 MW.
- Evacuation infrastructure:
Muno 1 30/220 kV set: Transformer substation with power transformer 220/30 kV of 80 MVA.
Muno 2 30/220 kV set: Transformer substation with power transformer 220/30 kV of 120 MVA.
LAAT 220 kV SET Muno 2-SET Muno 1: Airline 220 kV of 6.42 Km in length and conductor 402-AL1/52-ST1A (LA-455 CONDOR).
LAAT 220 kV SET Muno 1-SEC Templars: Airline 220 kV of 26 Km in length and conductor 402-AL1/52-ST1A (LA-455 CONDOR).
SEC Templars 220 kV: Electrical disconnector substation 220 kV.
LAAT 220 kV SEC Templars - SET Promoters Muruarte 220 kV: Airline 220 kV of 28.02 Km in length and conductor 402-AL1/52-ST1A (LA- 455 CONDOR).
SET Promoters Muruarte 220/400 kV: Electrical substation of promoters with 2 input power transformers and an output position to evacuate the energy through a 400 kV High Voltage overhead line of the wind farms PE Muno, PE Templarios and PFV`s Serena Solar.
LAAT 400 kV SET Promoters Muruarte-SET Muruarte 400 KV: Airline of 400 kV of 60 meters in length and two conductors 806-AL1/56-ST1A (LA-860 LAPWING).
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Start date to procedure:11/03/2021.
- Public Information BOE: 06/10/2021.
- Public information BOP Zaragoza: 06/10/2021.
- Public information BOP Navarra: 06/11/2021.
- DIA Resolution: 03/04/2024.