PEol-663 AC. Zibal, Almaz, Gomeisa, Lynx, Fulu, Tejat, Zosma wind installation of 49.50 MW each and its evacuation infrastructure in the provinces of Huesca and Zaragoza.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Bujaraloz and La Almolda (Zaragoza); Villanueva de Sigena, Castejón de Monegros, Sena and Valfarta (Huesca).
Power: 346.5 MW.
Holder: Inexhaustible Energy of Zibal, S.L., Inexhaustible Energy of Almaz, S.L., Inexhaustible Energy of Gomeisa, S.L., Inexhaustible Energy of Lynx, S.L., Inexhaustible Energy of Fulu, S.L., Inexhaustible Energy of Tejat, S.L. and Inexhaustible Energy of Zosma, S.L. Being Inexhaustible Energy of Zibal, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Zibal wind installation of 49.5 MW.
- Almaz wind installation of 49.5 MW.
- Gomeisa wind installation of 49.5 MW.
- Lynx wind installation of 49.5 MW.
- Fulu wind installation of 49.5 MW.
- Tejat wind installation of 49.5 MW.
- Zosma wind installation of 49.5 MW.
The evacuation infrastructure is included in the files Peol-577 AC, PEol-556, PEol-662 AC and PV Atik.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 07/22/2021.
- Public Information BOE: 12/31/2021.
- Public information BOP Zaragoza: 04/02/2022.
- Public information BOP Huesca: 12/30/2021.
- DIA Resolution: 28/08/2023.
- Resolution AAP Zibal: 27/11/2023.
- Resoultion AAP Almaz: 27/11/2023.
- Resoultion AAP Lynx: 27/11/2023.
- Resoultion AAP Fulu: 27/11/2023.
- Resoultion AAP Tejat: 27/11/2023.
- Resoultion AAP Zosma: 27/11/2023.
- Resoultion AAP Gomeisa: 24/10/2024.