PEol-577 AC. Maia, Vela and Octante wind installations of 49.5 MW each and their evacuation infrastructure in the provinces of Huesca and Barcelona.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Castejón de Monegros, Sena and Villanueva de Sigena (Huesca).
- Evacuation infrastructure: Sena (Huesca); Abrera, Castellbisbal, Els Hostalets de Pierola, Esparraguera, Olesa de Montserrat, Rubí y Ullastrell (Barcelona).
Power: 148.50 MW.
Holder: Inexhaustible Energy of Maia, S.L., Inexhaustible Energy of Vela, S.L. and Inexhaustible Energy of Octant, S.L. Being Inexhaustible Energy of Maia, S.L. The promoter that represents all the mercantiles.
Projects contained:
- Maia wind installation of 49.5 MW.
- Wind installation of Vela of 49.5 MW.
- Octante’s wind installation of 49.5 MW.
- Evacuation infrastructure:
Transformer substation Sena 30/400 kV.
High Voltage Airline 400 kV of 5,300 Km from SET Sena - SET Almolda.
Transformer substation Almolda 30/400 kV.
High Voltage Airline 400 kV of 1,922 Km from SET Almolda-SET Bujaraloz.
400 kV 2,254 km High Voltage Overhead Line from SET Bajo Cinca R4-SET Promoters Rubi R4.
Transformative substation Promoters Rubi R4.
Transformer substation Promoters Rubi R2
High Voltage Overhead Line 400 kV of 18,811 Km from SET Promoters Rubi R4-SET Rubi 400 REE.
The rest of the shared evacuation infrastructure is included in the PEol-556 file.
STATUS OF THE FILE:
Prior administrative authorisation and environmental impact statement:
- Starting date for processing: 07/22/2021
- Public information BOE 26/10/2021
- Public information BOP Huesca: 10/25/2021
- Public information Official Diari of the Generalitat Catalunya: 11/17/2021
- DIA Resolution: 28/08/2023.
- Resolution AAP Maia: 24/11/2023.
- Octant AAP Resolution: 27/11/2023.
- Resolution AAP Vela: 24/10/2024.