PEol-246. Valiente II wind installation of 88.4 MW and its evacuation infrastructure in the province of Huesca.
INFORMATION OF THE FILE:
Municipal terms:
- Park: Gurrea de Gállego (Huesca).
- Evacuation infrastructure: Gurrea de Gállego, Alcalá de Gurrea, Almudévar, Lupiñén-Ortilla and la Sotonera (Huesca).
Power: 88.4 MW.
Holder: Villar Mir Energía, S.L.
Projects contained:
- Valiente II wind installation of 88.4 MW.
- Evacuation infrastructure:
Underground lines of 30 kV.
Substation 30/220 kV.
Línea Aérea de Alta Tensión 220 kV Set Valiente II - Set Esquedas de 220 kV.
STATUS OF THE FILE:
Prior Administrative Authorization, Environmental Impact Statement, Construction Administrative Authorization and Public Utility Statement:
- Starting date for processing: 18/07/2019.
- Public Information BOE: 06/09/2020.
- Public information BOP Huesca: 11/06/2020.
- DIA Resolution: 04/21/2022.
- AAP Resolution: 04/24/2023
Prior administrative authorization of the modifications derived from the resolution of the environmental impact statement and administrative authorization of construction.
- Public Information BOE: 25/05/2023.
- Public information BOP Huesca: 25/05/2023.
- Resolution modification AAP and AAC: 05/07/2024.
Modification of the administrative authorization of construction and declaration, in particular, of public utility: